Operation CHARM: Car repair manuals for everyone.

Cylinder Head Assembly: Labor Times

Standard HoursManufacturer Warranty HoursSkill LevelNotes
Replace
Manual Trans
Right Bank35.125.1AIncludes: R&I Cylinder Head, Transfer All Necessary Components, Grind All Valves & Make All Necessary Adjustments.
Left Bank35.625.5AIncludes: R&I Cylinder Head, Transfer All Necessary Components, Grind All Valves & Make All Necessary Adjustments.
Both Banks47.234.2AIncludes: R&I Cylinder Head, Transfer All Necessary Components, Grind All Valves & Make All Necessary Adjustments.
Auto Trans
Right Bank36.726.6AIncludes: R&I Cylinder Head, Transfer All Necessary Components, Grind All Valves & Make All Necessary Adjustments.
Left Bank37.527.0AIncludes: R&I Cylinder Head, Transfer All Necessary Components, Grind All Valves & Make All Necessary Adjustments.
Both Banks48.535.7AIncludes: R&I Cylinder Head, Transfer All Necessary Components, Grind All Valves & Make All Necessary Adjustments.