Operation CHARM: Car repair manuals for everyone.

Main Relay (Computer/Fuel System): Testing and Inspection





CIRCUIT DIAGRAM





INSPECTION USING SCAN TOOL





HARNESS INSPECTION PROCEDURE

COMPONENT TEST PROCEDURE





NOTE: When applying battery voltage directly, make sure that it is applied to correct terminal. Otherwise, the relay could be damaged.





1. Connect a 12V power supply (+) terminal to the terminal 6 of the multipoint fuel injection control relay and measure the voltages at terminals 2 and 1 when the (-) terminal is connected to and disconnected from the terminal 8.




Fig. 2 Control Relay Testing:





2. Connect a 12V power supply (-) terminal to the terminal 10 of the multipoint fuel injection control relay and check the continuity between terminals 3 and 4 when the (+) terminal is connected to and disconnected from the terminal 7.




Fig. 3 Control Relay Testing:





3. Connect a 12V power supply (+) terminal to the terminal 3 of the multipoint fuel injection control relay and measure the voltages at the terminal 4 when the (-) terminal is connected to and disconnected from the terminal 9.





4. If one of the above is improper, replace the multipoint fuel injection control relay.