Main Relay (Computer/Fuel System): Testing and Inspection
CIRCUIT DIAGRAM
HARNESS INSPECTION PROCEDURES
RELAY INSPECTION
1. Check for continuity of relay coil windings between terminal 4 (+) and 2 (-).
2. Check continuity of relay contacts between terminals 5 and 1.
3. Check continuity of relay contacts between terminals 5 and 3.
4. If faulty, replace the MFI control relay.
Tightening torque: MFI control relay 7-11 Nm (5.2-8.1 lb.ft.)