Fuel Pump Relay: Testing and Inspection
PROCEDURE
Inspect Relay Continuity.
1. Disconnect negative (-) terminal cable from battery.
CAUTION: Work must be started after 90 seconds from the time the ignition switch is turned to the LOCK position and the negative (-) terminal cable is disconnected from the battery.
Testing Relay Continuity:
2. Using an ohmmeter. check that there is continuity between terminals ST and E1.
3. Check that there is continuity between terminals +B and FC.
4. Check that there is NO continuity between terminals + B and FP.
If continuity is not as specified. replace the relay.
Inspect Relay Operation
Testing Relay Operation:
1. Apply battery voltage across terminals ST and E1.
2. Using an ohmmeter, check that there is continuity between terminals +B and FP.
If operation is not as specified, replace the relay.