FP 1.0 - 3.0
Special Tools:
Special Tools:
Special Tools:
SPECIAL TOOLS
NOTE: All or some of the special tools shown in the image are required to perform the testing procedures. If Mercedes special tools are not available, select tools may be substituted with an aftermarket equivalent.
Additional tools:
a. Fuel hose (500 mm, 20 in)
b. Measuring glass (1 liter minimum)
c. Stop watch
d. Multimeter Sun DMM-5, Fluke Model 23, 83, 85 or 87
Test Equipment Hook-up:
Test Equipment Hook-up:
PREPARATION FOR TEST
Connect test equipment as shown in images.
NOTE: The numbers in parentheses in the "Test Connection" column, for example (1.23), signify:
1 = Connector 1 on wiring diagram,
23 = Socket 23 on wiring diagram.
Test Steps FP 1.0 - 2.0:
TEST STEPS FP 1.0 - 2.0
Test Step FP 3.0:
TEST STEP FP 3.0
Figure 1:
FIGURE 1