Operation CHARM: Car repair manuals for everyone.

Secondary Air INJ Control Valve Replacement - Bank 2 (Single Pump System)

REMOVAL PROCEDURE
1. Remove the Air Cleaner Assembly.
2. Disconnect the vacuum lines.
3. Loosen and lower the pinch clamp connecting the bank 2 intermediate pipe/hose to the bank 2 shut-off valve.
4. Disconnect the hose from the shut-off valve.
5. Remove the 2 nuts securing the bank 2 AIR shut-off to the bracket.
6. Remove the bank 2 AIR shut-off valve from the bracket.

INSTALLATION PROCEDURE
1. Install the bank 2 AIR shut-off valve and new gasket to the bank 2 outlet pipe.

NOTE: Refer to Fastener Notice in Service Precautions.

2. Install the 2 nuts securing the shut-off valve to the bracket.

Tighten
Tighten the three nuts to 9 N.m (80 lb in).

3. Install the bank 2 intermediate pipe/hose and clamp to the shut-off valve.
4. Install the vacuum lines.
5. Install the air cleaner assembly.