Operation CHARM: Car repair manuals for everyone.

Installation

Installation
Installation is performed in reverse order, taking the following points into account.
1. Ensure perfect seating of dowel sleeves in crankcase.





2. Fix the converter in installation position with special tool 9595/1 (long).
3. Grease converter bearing journal with a thin coat of Olista Longtime 3 EP (available as spare part).





4. Carefully move transmission in and fasten to engine.
* Multiple-tooth nut
** Hexagon nut (fastening point omitted as of 5.5.98)





5. Remove fixing pins (special tool 9595/1).





6. Push vacuum pipe onto switch-over valve.

Note!
^ The two vacuum pipes must not be confused. Otherwise, transmission cooling will be inadequate.

A from vacuum reservoir
B to shut-off valve on transmission
7. Press end piece of selector lever cable onto the transmission lever using a pair of pliers. The end piece must be felt to engage.
8. Check adjustment of selector lever cable.
9. Check engine coolant level.