Procedures
272219 Removing and Installing Three-Phase Generator
Preliminary work
Preliminary work - three-phase generator
Disconnect battery.
Removing three-phase generator
Installation Position:
Unscrewing Fastening Screws:
1. Unscrew the two fastening screws -1, 2- and remove together with the deflection roller.
Unscrewing The Fastening Screws For The Vacuum Modulator:
2. Unscrew the two fastening screws -3- for the vacuum modulator.
Removing Three-phase Generator From The Engine:
3. Lift the right generator over the bracket on the engine -A-, then pull forwards and down -B- and raise clear of the engine from the rear -C-.
Disconnecting Electrical Connections:
4. Release and unplug the electrical connector -A-.
5. Unscrew fastening nut -B- for the B+ lead -4- and remove the B+ lead.
Installing three-phase generator
Installation Position:
Connecting Electrical Connections:
1. Place the three-phase generator on the engine and fit the B+ lead -4-, tightening with the fastening nut -B-. Tightening torque 11 ftlb..
2. Press in the electric plug until it clicks into place.
Positioning Three-phase Generator On The Engine:
3. Insert the three-phase generator into the engine area -C-, then push upwards -B- and lift over the bracket -A-.
Screwing Down Vacuum Modulator:
4. Position vacuum modulator over the three-phase generator and screw it down with the fastening screws -3-. Tightening torque 6.5 ftlb..
Screwing Down Fastening Screws:
5. Screw down three-phase generator with the two fastening screws -1, 2-. Tightening torque 34 ftlb. Tightening torque 34 ftlb..
Subsequent work
Subsequent work - three-phase generator
Connect battery.