| Standard Hours | Manufacturer Warranty Hours | Skill Level | Notes |
Resurface/Grind | 9.6 | 6.6 | A | Includes: R&R Cylinder Head And Make All Necessary Adjustments. |
Add the Following Operations If Performed With Valves, Grind. |
Valve Guides, Knurl |
Each | 0.2 | 0.0 | A | Add The Following Operations If Performed Along With Piston & Ring Jobs. |
Valve Guides, Renew |
Each | 0.4 | 0.0 | A | Add The Following Operations If Performed Along With Piston & Ring Jobs. |
Note |
To Ream Guide, Add | 0.1 | 0.0 | A | Add The Following Operations If Performed Along With Piston & Ring Jobs. |
Timing Belt, Renew | 0.7 | 0.0 | A | Add The Following Operations If Performed Along With Piston & Ring Jobs. |
Tune-Up | 0.5 | 0.0 | A | Add The Following Operations If Performed Along With Piston & Ring Jobs. |
Rocker Arm ASSY, Overhaul | 0.5 | 0.0 | A | Add The Following Operations If Performed Along With Piston & Ring Jobs. |
Head Removed | 2.4 | 1.4 | A | |