Pinpoint Test L: The Blower Motor Is Inoperative
Climate Control System
Pinpoint Tests
Pinpoint Test L: The Blower Motor is Inoperative
Refer to Wiring Diagrams Set 54, Climate Control System for schematic and connector information. Diagrams By Number
Normal Operation
Under normal operation, the blower motor relay coil receives ignition voltage through circuit CDC33 (VT/GN). The coil receives ground from the HVAC module through circuit CH123 (VT/GN) if any function selector position but OFF is selected. Voltage is supplied to the relay switch contact through circuit SBB12 (GN/RD). When the relay coil is energized, voltage is delivered to the blower motor through circuit CH402 (YE/GN). Ground for the blower motor is provided through circuit VH301 (YE/BU) from the blower resistor or the blower switch (HI). The blower resistor and blower switch is grounded through circuit GD138 (BK/WH).
- DTC B12AF Front Blower Motor Relay Drive Circuit Shorted to Battery Voltage - The module senses voltage on the relay coil ground circuit, indicating a short directly to voltage.
- DTC B12B0 Front Blower Motor Relay Drive Circuit Open or Shorted to Ground - The module senses no voltage on the relay coil ground circuit, indicating an open or a short directly to ground.
This pinpoint test is intended to diagnose the following:
- Fuse(s)
- Wiring, terminals or connectors
- Blower motor
- Blower motor relay
- Blower motor switch
- HVAC module
PINPOINT TEST L: THE BLOWER MOTOR IS INOPERATIVE
-------------------------------------------------
L1 CHECK THE HVAC MODULE FOR DTCs
- Ignition ON.
- Check the HVAC module for DTCs.
- Are any DTCs present?
Yes
For DTC B12AF, REPAIR circuit CH123 (VT/GN) for a short to voltage. CLEAR the DTCs. REPEAT the self-test. TEST the system for normal operation.
For DTC B12B0, CARRY OUT the blower motor relay component test.
If the relay tests OK, GO to L2.
No
GO to L3.
-------------------------------------------------
L2 CHECK THE RELAY COIL SUPPLY VOLTAGE
- Ignition OFF.
- Disconnect: Blower Motor Relay.
- Ignition ON.
- Measure the voltage between blower motor relay socket pin 1 and ground.
- Is the voltage greater than 10 volts?
Yes
REPAIR circuit CH123 (VT/GN) for an open. TEST the system for normal operation.
No
INSTALL a new Battery Junction Box (BJB). TEST the system for normal operation.
-------------------------------------------------
L3 CHECK CIRCUIT VH301 (YE/BU) FOR GROUND
- Ignition OFF.
- Disconnect: Blower Motor C2004.
- Turn the function selector switch to the PANEL position.
- Turn the blower motor switch to the HI position.
- Measure the resistance between blower motor connector C2004-1, circuit VH301 (YE/BU), harness side and ground.
- Is the resistance less than 5 ohms?
Yes
GO to L6.
No
GO to L4.
-------------------------------------------------
L4 CHECK CIRCUIT VH301 (YE/BU) FOR AN OPEN
- Disconnect: Blower Motor Switch C2357b.
- Measure the resistance between blower motor switch C2357b-2, circuit VH301 (YE/BU), harness side and blower motor C2004-1, circuit VH301 (YE/BU), harness side.
- Is the resistance less than 5 ohms?
Yes
GO to L5.
No
REPAIR circuit VH301 (YE/BU) for an open. TEST the system for normal operation.
-------------------------------------------------
L5 CHECK CIRCUIT GD138 (BK/WH) FOR AN OPEN
- Measure the resistance between blower motor switch C2357b-1, circuit GD138 (BK/WH), harness side and ground.
- Is the resistance less than 5 ohms?
Yes
INSTALL a new blower motor switch. TEST the system for normal operation.
No
REPAIR circuit GD138 (BK/WH) for an open. TEST the system for normal operation.
-------------------------------------------------
L6 CHECK A/C BLOWER MOTOR CIRCUIT CH402 (YE/GN) FOR VOLTAGE
- Ignition ON.
- Measure the voltage between blower motor C2004-2, circuit CH402 (YE/GN), harness side and ground.
- Is the voltage greater than 10 volts?
Yes
INSTALL a new blower motor. TEST the system for normal operation.
No
GO to L7.
-------------------------------------------------
L7 CHECK CIRCUIT CH402 (YE/GN) FOR AN OPEN
- Ignition OFF.
- Disconnect: Blower Motor Relay.
- Measure the resistance between blower motor relay connector pin 5, circuit CH402 (YE/GN) and blower motor C2004-2, circuit CH402 (YE/GN), harness side.
- Is the resistance less than 5 ohms?
Yes
GO to L8.
No
REPAIR circuit CH402 (YE/GN) for an open. TEST the system for normal operation.
-------------------------------------------------
L8 CHECK THE BLOWER MOTOR RELAY
- Connect: Blower Motor C2004.
- Ignition ON.
- Connect a fused jumper lead between blower motor relay socket pin 3, circuit SBB12 (GN/RD) and pin 5, circuit CH402 (YE/GN).
- Does the blower motor operate?
Yes
CARRY OUT the blower motor relay component test.
If the relay tests OK, GO to L9.
No
VERIFY BJB fuse 12 (40A) is OK. If OK, REPAIR circuit SBB12 (GN/RD) for an open. TEST the system for normal operation.
-------------------------------------------------
L9 CHECK THE MODULE CONNECTION
- Carry out the HVAC Module Cold Boot Process. HVAC Module Cold Boot Process
- Operate the system.
- Does the concern return?
Yes
INSTALL a new HVAC module. TEST the system for normal operation.
No
The system is operating correctly at this time. The concern may have been caused by a loose or corroded connector. TEST the system for normal operation.
-------------------------------------------------